Researchers proposed a two-stage framework to co-optimize electricity and computation for AI data centers. It quantifies how spatial and temporal workload flexibility increases hosting capacity. Temporal flexibility alone adds 21.26% capacity. Spatial flexibility alone adds 5.37%. Combined, they raise capacity by 34.44% to 6231.5 MW without new transmission lines. The coordinated approach yields 361.9 MW more than the sum of individual gains. It links workload routing and deferral to server power demand. The first stage maximizes hosting capacity. The second minimizes generation and carbon costs. An 8760-hour case study on a modified IEEE 118-bus system validates the findings.
What changed
Hosting capacity was limited by grid connection constraints without quantified workload flexibility benefits.
What it unlocks
Data centers can admit more capacity by routing interactive requests and deferring batch workloads across locations and time.
- 21.26% hosting capacity increase from temporal flexibility
- 5.37% from spatial flexibility
- 34.44% combined increase to 6231.5 MW
- 361.9 MW coordinated gain over individual sums
What you need to act on it
- existing transmission network capacity
- workload completion requirements
- transmission constraints