Research2026-11-07

SemiAnalysis visited Galaxy, a hyperscale AI datacenter campus in Inner Mongolia. It is planned for 800MW of IT capacity. The first 120MW phase was built in one year at a fifth of US costs. Envision Group owns and operates the campus. It also built the wind farms and power lines supplying it. A 5MW pilot hall uses solid-state transformers to deliver 800V DC directly to racks. This removes low-voltage transformers, UPS and rectifiers. Galaxy cools servers with a shared water loop and no central chiller plant. The campus is built-to-suit for two unnamed internet giants. Envision aims to supply over 60% of its power from its own wind farms. The region has 25GW of announced datacenter projects. Construction costs keep falling due to abundant labor and vertical integration.

What changed

US datacenters typically use AC UPS and central chillers, with modular builds and higher costs.

What it unlocks

Running a hyperscale AI campus on mostly self-supplied wind power with no central chillers and an 800V DC architecture.

  • 800MW planned IT capacity
  • 120MW first phase delivered in one year
  • 5MW 800V DC pilot with SSTs
  • 420MW wind farm capacity for 240MW load

What you need to act on it

  • wind-rich region
  • oversized renewable generation
  • battery storage integration
  • vertical integration of power and datacenter systems

Send this to someone who needs it

Shares the story and its sources. Nothing about you.

What does this mean for your job?

This is the story as everyone gets it. Once a week we send you the version written for your role — what changed, why it matters for the work you actually do, and one thing to try. Free while we tune it.